03-30-2013: 5 hrs

It's been a while since I can spend so much time working on airplane on weekends. I got the plumbing done for the fuel pump and filter. Then tigtened the fittings to the fuel valve. I used Permatex high temperature thread sealant to help seal the fitting. The NPT tapered fitting doesn't have a standard torque, and the fitting need to be aligned to a certain direction so the fuel lines can be joined to the valve, so I just go by "feel". Hope there will be no leaking. We will see.

The fuel system is almost done, just need make the spacer for the fuel valve, and make some final ajustment on the tubing. Also, I need to order floscan sensor so I can install it before closing the fwd deck. Just endless little things.

Since I still don't have the tube for fuel valve spacer, I moved on to the fwd deck structure. made various parts, and got all the way to fit the fwd top skin. Great progress today.


Tubing between pump and filter is done


Various parts for fuselage fwd superstructure fabricated


F7108B angle fabricated


F721D fabricated


Doubler is drilled with rib


Clip is match drilled


F7108B angle is match drilled


The bend angel is right


Cable bracket is drilled with center sub-panel


The assembly is primed and riveted together


Another view of the riveted assembly




Shop heads are looking good


Started clecoing superstructure together for fitting and drilling


Another view of the superstructure


Top skin is clecoed


Just another view of the clecoed top skin