06-29-2013: 1 hr


Marked the hole position on the left side skirt brace, than drilled the holes on top flange to #40. Also, use the holes on the left brace to match drill the right brace. AFter that, I drilled the lightening holes and cut the notches on the left brace


P.S. When match drilling holes on the righ brace, I put the 1/2" (shorter) flange as the top flange, while the 5/8" flange should be the top flange. I will need to order new part




Right side skirt is all drilled to frame


This brace is messed up, the hole should be drilled on the bottom flange in this picture