08-25-2012: 2 hrs

Started fabricating F796B, C, D spacers and angles. I found a left over 0.125x 4/3 x 3/4 angle that is long engouth to make two F796B. The dimension on drawing for F796B is about 1/8 longer, I had to trim off that much to fit the angle to the fuselage. I messed up the first F796B angle by trimming it to much. So, I had to find other stock angle. The only thing I can find is a very long stock angle from wing kit. I guess that should be the raw material I need use. I cut a length from the long piece to make the third one. The finshied F796B fit the fuselage well, I will drill them tomorrow.



F796C and D are fabricated



The left F796B fit is very good