11-14-2012: 3 hrs

Installed bellcrank, and riveted baggage floors. The floors are painted as well.


I riveted the cargo area vertical bulkhead to longeron. Look at the scratched primer. I will do some touch up later


The shop head of the rivet shown above


Due to severe misalignment between the floor and right side cover, I had to make the holes bigger. I will use a very fat aluminum pop rivet here. 


Close up view of the big fat rivet hole, they look good though


The fat rivet I will use is on the left. On the right is the LP4-3 rivet called out in plan


Floors are painted and clocoed to ribs


Left cargo floor is riveted using pop rivets


Both floors are riveted