11-15-2012: 1.5 hrs

I decided to install rudder cables now. I was worried because I didn't do this like most builders did, installing rudder cables before riveting the aft cargo side walls. I had to get the two snap bushings out of the F706 bulkhead and cargo vertical stiffener, which is painful. I tried all kinds of methods, finally I got them out all right. After that, the installation is easy. This is actually easy than I thought.

Then I went on working on the wear block for the should harness. I can't drill the nylon with smooth finish, and nylon is hard to deburr. Other than rough finish, the strength and functionality should be just fine. It's a wear block anyway. I can live with that. Once the strap cable is installed, no one will ever notice the tiny wear block behind the cargo bulkhead.


Rudder cables are installed


The aft end of rudder cable


Wear block. Look at how rough the finish is. I need find a better way to cut nylon. But it won't affect its function


Wear blocks are clecoed