04-14-2013: 3 hrs





Center reinforcement web and clip are riveted together


ADAHRS #2 mount is really just two angles because the right bay is narrower than the left. But this should work well. It feels pretty stiff. I might not use the second ADAHRS initially, just want to have the provision ready just in case I will need the second unit in the future


This is how the unit is installed to the mounting brackets viewed fwd from under. I have to use some spacers to meet the 1-degree alignment limit for the unit


I used my iphone app to check the alignment, here is the iphone on longeron, set to 0-degree


The unit is within the 1-degree alignment limit