Wings

05-09-2011: Ordered standard wing kit

07-11-2011: The wing kit is scheduled for delivery on 7/13, finally I will be busy again

07-13-2011: Wing kit arrived today. - 1 hr

07-14-2011: Inventoried wing kit - 2 hrs

07-17-2011: Building wing stand - 2.5 hrs

07-18-2011: Inventoried wing kit, done, no missed parts - 1 hr

07-19-2011: Riveted fuel tank attaching nutplates on right spar - 2.5 hr

07-20-2011: Nutplates on right spar done, countersunk nutplate rivet holes on left spar - 3.5 hr

07-22-2011: Leaving for Oshkosh EAA Fly-in, no building in the next week

07-30-2011: Back from Oshkosh, work on finishing nutplate and tie down on right spar- 7 hrs

07-31-2011: Finish tie down bar assembly on left main spar, finish wing stand - 4 hrs

08-02-2011: Deburr edge of left rear spar channel and doublers  - 2 hrs

08-03-2011: Final drilled and deburred left rear spar components - 2 hrs

08-04-2011: Dimpled, primed left rear spar components, started riveting - 3 hrs

08-06-2011: Deburred all W711 inboard main rib - 8 hrs

08-07-2011: Worked on right rear spar, primed all parts - 3 hrs

08-08-2011: Riveted right rear spar - 1 hrs

08-09-2011: Deburred 2 W408 and 1 W712 ribs - 1 hr

08-10-2011: More deburring, W712 and W710 ribs done - 1.5 hr

08-11-2011: Finished deburring W408 and W709 ribs, only tank ribs left - 2.5 hr

08-13-2011: Deburr tank ribs, no picures - 1.5 hr

08-15-2011: Deburr tank ribs, no pictures - 0.5 hr

08-16-2011: Finished deburring all wing and tank ribs - 1 hr

04-03-2012: Installed aileron bellcrank brackets, bellcrank assembly - 2 hrs

04-04-2012: Aileron hinge brackets - 0.5 hr

04-05-2012: Aileron hinge brackets - 2.5 hrs

04-06-2012: Aileron hinge brackets riveted to wing - 3 hrs

04-07-2012: Flap braces and aileron gap fairing - 3 hrs

04-08-2012: Flap braces and Aileron gap fairing - 3 hrs


Right Wing: 46.5 hrs

08-17-2011: Straightened and fluted ribs for right wing - 2 hrs

08-18-2011: Opened bottom tooling holes to 5/8" for wiring in right wing, match drilling - 2 hrs

08-21-2011: Deburred and primed rib wing ribs, opening top tooling holes to 1/4" - 3 hrs

09-08-2011: Riveted right main ribs to front spar - 2 hrs

09-10-2011: Finished riveting main ribs to main and rear spars, right wing on stand - 4 hrs

09-11-2011: Added support to rear spar on wind stand, jacked right wing skeleton - 1 hr

09-12-2011: Fitted top and bottom skins to skeleton - 3 hrs

09-14-2011: Check and correct right wing twist before final drilling main skins - 1.5 hrs

09-15-2011: Top and bottom main skins final drilled - 2 hrs

10-10-2011: Wing skin, started de-blueing the panel along rivet line - 0.5 hr

10-13-2011: Deburred top skin, dimpled top skin and wing ribs, more to be done - 2 hrs

10-14-2011: Inboard top skin de-vynled, deburred - 2 hrs

10-15-2011: Dimpled top skin, dimpled all ribs, countersunk spar channel top side - 4 hrs

10-16-2011: All preparation done for wing ribs and spars. Then worked on leading edge - 5 hrs

10-25-2011: Tapped the tied down bracket  - 0.5 hrs

12-28-2011: Spacer between eye bolt and tie down bracket, rivets underneath the tank  - 0.5 hrs

12-30-2011: Riveted spanwise row of rivets of leading edge, wing cradle built  - 3 hrs

12-31-2011: Wing cradle complete, fuel tank installed - 3.5 hrs

01-01-2012: Right wing top skin riveting - 2 hrs

01-02-2012: Right wing top skins riveted, wing moved to cradle - 3 hrs


Right Leading Edge: 17.5 hrs

09-16-2011: Leading edge cradle - 1 hr

09-17-2011: Right Leading edge - 2 hrs

09-18-2011: Leading edge end rib and join plate - 1.5 hrs

10-16-2011: All preparation done for wing ribs and spars. Then worked on leading edge - 5 hrs

10-18-2011: Finished splice strip, re-countersunk spar channel for tighter fit with skin - 2 hrs

10-19-2011: Finished leading edge - 2 hrs

10-20-2011: Riveted leading edge ribs to spar web, only finished 2 ribs today - 1 hrs

10-24-2011: Riveting the rib to the spar, tough riveting, not done yet - 2 hrs

10-25-2011: Finished riveting rib to the spar - 1 hrs


Right Fuel Tank: 67 hrs

09-20-2011: Right fuel tank Z brackets  - 1.5 hrs

09-21-2011: Fuel tank Z brackets nutplates installed  - 2 hrs

09-22-2011: Z brackets primed and bolted to spar - 2 hrs

09-23-2011: Fuel tank put together and fitted to spar - 1.5 hrs

09-24-2011: Fuel tank, Z brackets match drilled, tank stiffeners made, skin countersunk - 7 hrs

09-25-2011: Tank to fuselage attaching bracket fabricated, ribs and stiffener dimpled - 4 hrs

09-27-2011: Tank skin de-vynled , access holes cut - 1.5 hr

09-28-2011: Fuel tank access plate, fuel cap flange - 2  hrs

09-29-2011: Fuel tank drain flange drilled, skin deburred, dimpled, edge smoothed - 2.5 hrs

10-01-2011: Fuel tank, pro-seal applied on stiffeners, fuel cap flange, and drain - 6.5 hrs

10-02-2011: Fuel tank sealing, riveted stiffeners, cap flange and drain, pro-sealed ribs - 8 hrs

10-03-2011: Fuel tank skin riveted to interior ribs on top side - 3.5 hrs

10-04-2011: Fuel tank skin riveted to interior ribs on bottom side - 3 hrs

10-05-2011: Fuel tank, outboard rib fay sealed - 1 hrs

10-06-2011: No actual building, read about fuel return line, decided not to have one - 3 hrs

10-07-2011: Fuel tank inboard rib riveted - 4 hrs

10-08-2011: Fuel tank access plate, vent line, fuel sender, fuel pickup line - 5 hrs

10-09-2011: Fuel tank baffle plate, right fuel tank done - 8 hrs

10-25-2011: Made a stupid mistake on the tank, have to build another one - 1 hrs


Ailerons:  32 hrs

10-22-2011: Right aileron stiffeners, cut, trimmed, deburred, primed, dimpled - 2.5 hrs

10-23-2011: Right aileron skin stiffener riveted, bent, worked on spar - 4 hrs

10-26-2011: Leading edge and trailing edge skin final match drilled - 2 hrs

10-27-2011: Counterbalance pipe work - 1 hr

10-30-2011: Deburred, primed, riveted, right aileron done - 5 hrs

11-01-2011: Built a long brake for aileron, worked on left aileron stiffeners - 1 hrs

11-02-2011: Primed, dimpled left aileron stiffeners and skin - 1.5 hrs

11-03-2011: Riveted stiffeners to skin for left aileron, skin bent - 2.5 hrs

11-04-2011: Left aileron spar - 1.5 hrs

11-05-2011: Spar reinforcement plate riveted, skins and main ribs match drilled to spar - 4 hrs

11-06-2011: Left aileron parts are dimpled and primed, started final riveting - 4 hrs

11-07-2011: Left aileron done - 3 hrs


Right Fuel Tank #2: 57 hrs

11-08-2011: Z brackets drilled, nutplates installed, baffle clecoed to Z brackets  - 2 hrs

11-09-2011: Deburred ribs, positioned and drilled rib/baffle/Z bracket  - 3 hrs

11-11-2011: Tank stiffeners cut and trimmed, skin de-vynled  - 3 hrs

11-12-2011: Ribs, baffle, skin, Z brackets clecoed, drilled, and trimmed for fitting with LE- 5 hrs

11-13-2011: Fabricated tank/fuselage attaching bracket, cut access hole on inboard rib - 3 hrs

11-15-2011: Brkt and reinfrcmnt plate drilled, ring and nutplates riveted to inbrd rib- 3 hrs

11-16-2011: Drilled fuel cap flange and fabricated vent line support- 1 hr

11-17-2011: Drain flange drilled to skin, skin deburred, dimpled using fuel tank dimple die -2.5hrs

11-18-2011: Ribs deburred and dimpled, baffle deburred, tank assy clecoed - 2 hrs

11-19-2011: Tank assy positioned, screw holes drilled, started riveting/sealing stiffeners - 4 hrs

11-20-2011: Finished riveting/sealing stiffeners, cap flange and drain flange - 2.5 hrs

11-23-2011: Cleaned all ribs, riveted/sealed three ribs - 5 hrs

11-24-2011: Riveted/sealed the other two interior ribs, riveted reinforce plate to outbrd rib - 4 hrs

11-26-2011: Riveted/sealed the outboard rib - 2 hrs

11-29-2011: Riveted/sealed inboard rib and attaching bracket - 2.5 hrs

11-30-2011: Vent line - 1 hr

12-01-2011: Access plate - 1 hr

12-03-2011: Access plate finished - 2 hrs

12-04-2011: Baffle riveted and sealed - 6 hrs

12-28-2011: Fuel sender wire replaced with correct bents, access plate screwed on - 2 hrs

12-29-2011: Right fuel tank is tested, leak free - 0.5 hr


Flaps: 34 hrs

12-05-2011: Right flap spar deburred, ribs clecoed on - 1.5 hrs

12-06-2011: Drilled rib to bottom skin for right side flap - 1 hr

12-07-2011: Hing and top skin final drilled, including FL-708 shims - 2 hrs

12-08-2011: Prepare for final riveting - 2 hrs

12-10-2011: Flap preparation for final riveting - 2.5 hrs

12-11-2011: Deburring and priming right flap parts, get ready for final riveting - 3.5 hrs

12-12-2011: Right flap riveting - 3.5 hrs

12-13-2011: Right flap riveting, a deviation is made, Van's said it's OK - 3 hrs

12-20-2011: Left flap spar and rib work - 2 hrs

12-23-2011: All skins, spar, ribs match drilled, FL-706A/B match drilled - 3.5 hrs

12-24-2011: Deburring, priming. Fabricated rib reinforcement plate to address SED - 3 hrs

12-25-2011: Finished all dimpling and priming, started riveting the left flap - 3.5 hrs

12-26-2011: Complete both flaps - 3 hrs


Push Rods: 4.5 hrs

12-27-2011: Complete small push rods - 2 hrs

12-28-2011: Started working on big push rod - 1 hrs

12-29-2011: Finished the stick to bellcrank push rods - 1.5 hrs


Left Wing: 46 hrs

01-02-2012: Straightened and fluted ribs for left wing - 2 hrs

01-03-2012: Clecoed main ribs to spar, only half way through - 2 hrs

01-04-2012: Clecoed all main ribs to front and rear spars, ready for final drill - 2 hrs

01-05-2012: Final drill main ribs to spars, deburred ribs and rear spar - 3.5 hrs

01-07-2012: Primed main ribs, riveted all main ribs to front spar, except the outboard rib - 5 hrs

01-08-2012: Skeleton is all riveted, moved to wing stand - 3 hrs

01-10-2012: Wing walk doubler, top skins fitted and alignment checked - 2 hrs

01-11-2012: Bottom skins clecoed to skeleton for final drill - 0.5 hr

01-12-2012: Final drilled top skins, not done yet - 0.5 hr

01-13-2012: Finished final drilling top skins, started final drilling bottom skins - 0.5 hr

01-16-2012: Finished final drilling bottom skins - 1 hr

03-01-2012: Countersunk main spar flange and deburred spar - 2.5 hrs

03-03-2012:  Deburred and dimpled ribs, no pictures to show  - 2.5 hrs

03-05-2012:  Deburred and dimpled walk doubler, deburred inboard top skin- 1.5 hrs

03-06-2012:  Inboard top skin edge smoothed, interior primed at rivet lines - 1 hr

03-11-2012:  Top skins primed and dimpled, no pictures today - 1.5 hrs

03-12-2012:  Wing spar countersunk holes primed, top skins clecoed - 1 hr

03-25-2012:  Rear spar dimpled and touched with countersunk, tie down bracket tapped - 2.5 hr

03-27-2012:  Stall warning wiring installed, started riveting leading edge, tank test - 1 hr

03-28-2012:  Leading edge ribs riveted to spar web - 1.5 hrs

03-29-2012:  Leading edge riveted to spar, top skins clecoed for final riveting - 1.5 hrs

03-30-2012:  Tank is mounted to the spar, ready for riveting top skins - 1 hr

03-31-2012:  Riveting top skins. Inboard and half outboard are done  - 4 hr

04-01-2012:  Top skins riveted, left wing on cradle  - 2.5 hr

Left Leading Edge: 16.5 hrs

01-24-2012:  Clecoed left leading edge together, fitted to spar - 1.5 hrs

01-26-2012:  Inboard leading edge rib, joint plate, final drilled leading edge - 2.5 hrs

02-23-2012:  De-vynled skin, deburred and primed ribs - 2 hrs

02-24-2012:  Deburred and primed skin, dimpled ribs, no pics today - 1.5 hrs

02-25-2012:  Dimpled skin, worked on stall warner instl  - 3 hrs

02-26-2012:  Stall warner finished, leading edge riveted  - 6 hrs


Left Fuel Tank: 46.5 hrs

01-30-2012:  Z bracket to spar holes are drilled, waiting for k1000-3 nutplates - 1.5 hrs

02-01-2012:  Clecoed tank ribs to tank skin - 1.5 hrs

02-04-2012:  Nutplates on Z brackets and spar web, tanked fitted to spar - 3 hrs

02-05-2012:  Tank parts match/final drilled, skin countersunk for baffle - 4.5 hrs

02-07-2012:  Deburred tank skin and ribs, except stiffener rivet holes, no pictures - 2 hrs

02-08-2012:  Baffle deburred, stiffener fabricated, drilled and deburred - 2 hrs

02-09-2012:  Tank/fuselage attaching bracket, reinforcement plate and ring - 2.5 hrs

02-11-2012:  Nutplates installed to reinforcement ring, fuel cap drilled - 1.5 hrs

02-12-2012:  Drain plug match drill, smooth skin edges, dimpled all tank parts - 2.5 hrs

02-14-2012:  Stiffeners and drain flange riveted and sealed - 2.5 hrs

02-15-2012:  Fuel cap flange and the interior rib next to the outboard rib riveted, no pics - 2.5 hrs

02-16-2012:  One more interior rib riveted and sealed - 2 hrs

02-17-2012:  Third interior rib riveted and sealed, no picture to show - 2 hrs

02-18-2012:  All interior ribs riveted and sealed - 3 hrs

02-22-2012:  Outboard rib, vent line, inboard rib vent line fitting - 2.5 hrs

03-17-2012:  Inboard rib, vent line done - 2.5 hrs

03-18-2012:  Access plate done - 1.5 hrs

03-20-2012:  Deburred and smoothed edge of baffle plate, no pictures today - 0.5 hrs

03-22-2012:  Baffle plate riveted - 4 hrs

03-24-2012:  Baffle plate rivet heads sealed, access plate installed  - 2.5 hrs

03-30-2012:  Tank is tested leak free, balloon stayed inflated for 3 days, can still going strong


Wiring and Bottom Skins Riveting:

12-16-2012:  Started wiring for wings - 2 hrs

12-31-2012:  Installed flap and aileron on left wing - 3 hrs

01-01-2013:  Flap and aileron on right wing, conduit on right wing - 7 hrs

01-02-2013: Wiring conduit on left wing - 1.5 hrs

01-03-2013:  RTV between wiring conduits and ribs - 1 hr

01-04-2013:  Deburr bottom skins - 2 hrs

01-05-2013:  Primed and dimpled left bottom skins, wired right wing - 3 hrs

01-06-2013:  Made sure there is no plastic cover left in the right fuel tank - 2 hrs

01-09-2013:  Deblued left bottom skins - 1 hr

01-10-2013:  Cut bottom skin for pitot mount - 2.5 hrs

01-11-2013:  dd - 2.5 hrs

01-14-2013:  Drilled pitot heater control box to rib - 1.5 hrs

01-15-2013:  Pitot mast work, drilled the reinforcement angle to rib - 1.5 hrs

01-16-2013:  Dimpled left bottom skin, installed nutplate, pitot tube joined to mast - 1.5 hrs

01-19-2013:  Pitot tube line routing, left wing re-wiring - 6 hrs

01-21-2013:  Adjust left aileron bell crank to aileron push rob - 1 hr

01-22-2013:  Rivet left bottom skin0 - 2 hrs

01-26-2013:  Left wing bottom skins riveted - 10 hrs

01-27-2013:  Right wing inboard bottom skins riveted - 3 hrs

01-28-2013:  Right wing outboard bottom skins riveting - 1 hr

01-29-2013:  Right wing outboard bottom skins riveting - 1.5 hrs

01-30-2013:  Right wing outboard bottom skins riveting - 1 hr

01-31-2013:  Right wing outboard bottom skins riveting - 2 hr

02-01-2013:  Right wing flap wing hinge - 1 hr

02-02-2013: Wing mating, back to work on fuselage - 2.5 hrs

 