Shawn Li's RV-7 Construction Log

  • Home
  • Construction Log by Dates
  • Construction Deviation and Analysis
  • RV-7 In Action
  • Analysis
  • Phase I Log
  • On Going Maintenance
  • Maintenace Info


Fuselage

01-25-2012: Ordered standard fuselage kit, slider canopy, manual aileron trim

04-10-2012: Fuselage kit arrived, inventory - 1.5 hrs


Firewall (14 hrs)

04-12-2012: Inventory, fire wall - 3 hrs

04-13-2012: Firewall drilled - 2 hrs

04-14-2012: Spacer, Stiffener, doublers fabricated, firewall edge smoothed - 2.5 hrs

04-15-2012: All firewall parts deburred, stiffeners primed, started riveting - 4.5 hrs

04-16-2012: Firewall complete, started center section bulkhead - 2 hrs


Bulkheads (40.5 hrs)

04-17-2012: Center section bulkhead - 3 hrs

04-18-2012: Control column mouting brackets - 1.5 hrs

04-19-2012: Control column mouting brackets, nutplate - 2.5 hrs

04-20-2012: F704A nutplates, cover support web - 1.5 hrs

04-21-2012: F704 fwd buckhead all riveted,  - 4 hrs

04-22-2012: F704 bulkheads done  - 2 hrs

04-24-2012: F705 bulkhead, F705B bar and F605C doublers are done  - 1.5 hrs

04-26-2012: F705 bulkhead, lower rear spar attachment drilled  - 1.5 hrs

04-27-2012: F705 bulkhead, seat belt anchors drilled, lower bulkhead parts primed  - 2 hrs

04-28-2012: F705 bulkhead done  - 5 hrs

04-29-2012: Flap bearing block drilled and fitted  - 1 hr

05-08-2012: 706 bulkhead, deburred, fluted, primed  - 1.5 hr

05-10-2012: 729C stiffener, 707 bulkhead deburring  - 1.5 hr

05-12-2012: 707 bulkhead deburred and pirmed  - 1 hr

05-13-2012: F728 and F729 bellcrank ribs - 1.5 hrs

05-17-2012: Riveted F729 to F726 bottom - 1.5 hrs

05-18-2012: F708 bulkhead deburred and primed - 1.5 hrs

05-19-2012: F709, F710 - 1.5 hrs

05-26-2012: F709, F710, F711 and F712 bulkheads done - 3 hrs


After Fuselage (39.5 hrs)

05-27-2012: Longerons are bent - 1.5 hrs

05-31-2012: Built three sawhorses for fuselage construction - 2.5 hrs

06-01-2012: Trim tail cone for tailwheel mount - 1.5 hrs

06-02-2012: Fit F711, F712 to tail cone, tail wheel spring mount fitting - 3.5 hrs

06-03-2012: Cut J stringer, clecoed aft fuselage together - 2.5 hrs

06-08-2012: Trimmed J chanels - 1 hr

06-09-2012: Drilled J chanels and tail cone - 3 hrs

06-11-2012: Drilled aft fuselage, and took it apart, some problems on tail cone - 3 hrs

06-12-2012: Riveted tail cone - 3 hrs

06-14-2012: Deburred aft fuselage parts - 3 hrs

06-16-2012: Deburred, primed, dimpled right side skin - 2 hrs

06-17-2012: Deburred, primed, dimpled bottom skin, clecoed aft fuse together  - 2.5 hrs

06-18-2012: Started riveting, set all bottom rivets  - 1.5 hrs

06-19-2012: Riveting  - 1 hr

06-20-2012: Riveting, with a minor mistake  - 3 hr

06-21-2012: More riveting  - 2 hrs

06-22-2012: More riveting  - 2 hrs

06-23-2012: Finished aft fuselage for now  - 1 hr


Center and Fwd Fuselage (105.5 hrs) 

06-25-2012: Fabricated F916C  - 0.5 hr

06-26-2012: Enlarged cut out for 4 seat ribs - 1 hr

06-29-2012: Continued deburring seat ribs, not done yet - 1 hr

07-01-2012: Finished deburring seat ribs, center section clecoed - 3 hrs

07-03-2012: Re-orgnized garage to make room for center section, clecoed bottom skin - 1 hr

07-06-2012: Drilled bottom skin, fitted corner ribs - 2.5 hrs

07-07-2012: Finishing drilling center fuselage, crotch strap bracket - 3.5 hrs

07-08-2012: Preparing center fuselage section - 3.5 hrs

07-09-2012: Deburred, primed baggage ribs, trimmed seat belt strap brackets - 2.5 hrs

07-10-2012: Ribs, F704 bottom flange dimples, platenuts on ribs, crotch strap brackets - 3 hrs

07-12-2012: Riveted crotch strap bracket, started riveting seat ribs - 2.5 hrs

07-13-2012: Seat ribs riveted to F704 bulkhead - 1.5 hrs

07-14-2012: Seat ribs and baggage ribs riveted to F705 bulkhead - 1.5 hrs

07-15-2012: Bottom skin F776 deburred - 1.5 hrs

07-17-2012: Bottom skin F776 primed and clecoed to structure - 1 hrs

07-18-2012: Bottom skin riveting - 2.5 hrs

07-22-2012: Bottom skin riveting done - 3 hrs

07-23-2012: Longerons twisted, and F721 rails are drilled to longerons - 1.5 hrs

07-24-2012: Longerons trimmed and slotted, left F715 end seat rib drilled - 3 hrs

07-25-2012: Right F715 end seat rib drilled - 0.5 hr

07-26-2012: Joined center and aft fuselage, clecoed on side skins - 2 hrs

07-27-2012: Arm rests and conical bents - 3 hrs

07-28-2012: Inserted end seat ribs, started drilling longerons - 2 hrs

07-31-2012: Drilled right side longeron to side skins - 2.5 hrs

08-01-2012: Drilled left side longeron to side skins - 1.5 hrs

08-06-2012: Finished drilling longerons, fabricated F704 straps, firewall on - 2.5 hrs

08-07-2012: Fit and measure firewall position - 2 hrs

08-08-2012: Drilled firewall to skins - 2 hrs

08-09-2012: Aux longerons F-713 - 2 hrs

08-10-2012: Drilled F-713 to skins and engine mount brackets - 2 hrs

08-16-2012: Fabbed F719B clips, worked on fwd stiffeners F719 - 1.5 hrs

08-17-2012: Drilled fwd stiffeners F719 and F719B clip - 1.5 hrs

08-19-2012:  F717 lower longerons fabricated and drilled, fixed F719 short EM w/ strap - 4 hrs

08-20-2012:  Enlarged rudder cable holes on fwd bulkhead - 0.5 hr

08-21-2012:  F684 gusset fit - 1.5 hrs

08-22-2012:  F684 gusset drilled - 2.5 hrs

08-23-2012:  Replaced F719-L fwd skin stiffener - 0.5 hr

08-24-2012:  Nutplates on F902, F7101 reinforcement plate drilled to F902 - 2 hrs

08-25-2012:  F796B angle fabircated - 2 hrs

08-26-2012:  F796B angles drilled, Rudder and brake pedal work - 3 hrs

08-28-2012:  Brake pedals complete - 3.5 hrs

08-30-2012:  Clecoed baggage side ribs, drilled gear attach web to side skins - 0.5 hr

09-01-2012:  Brake pedal and cylinders, rudder block - 3 hrs

09-02-2012:  Trimmed rudder bars to length, drilled skin stiffeners for rudder blocks  - 1.5 hrs

09-03-2012:  Rudder bar center support bracket  - 1.5 hrs

09-04-2012:  Rudder center brace F6118 and block F6115 drilled  - 3 hrs

09-05-2012:  Bottom skin drilled, floor stiffeners drilled  - 3.5 hrs

09-06-2012:  Side skin drill, baggage frame  - 2.5 hrs

09-07-2012:  More fuselage drilling  - 2 hrs

09-08-2012:  Misc. preparation work for fuselage disassembling  - 4 hrs


Fwd Fuselage Preparation (44 hrs)

09-09-2012:  Fuselage disassembling, deburring  - 5 hrs

09-10-2012:  Prepared F902 bulkheads, fabbed shims  - 1.5 hrs

09-11-2012:  Deburring and priming  - 1.5 hrs

09-12-2012:  Right side skin deburring - 2.5 hrs

09-13-2012:  Left side skin deburring - 1.5 hrs

09-14-2012:  Finished left side skin deburring - 1 hr

09-15-2012:  Painted left side skin, center fuselage off   - 2 hrs

09-17-2012:  Prepared center fuselage, F706 bulkhead, aft fuselage - 3 hrs

09-18-2012:  Deburred and dimpled aft fuselage - 1.5 hrs

09-20-2012:  Countersunk right longeron - 1 hr

09-21-2012:  Countersunk left longeron - 1 hr

09-22-2012:  deburred and primed longeron - 1 hr

09-23-2012:  Countersunk fwd skin stiffeners - 0.5 hr

09-25-2012:  Installed Dynon autopilot pitch servo bracket - 2 hrs

09-26-2012:  ELT brackets installation - 2.5 hrs

09-27-2012:  Finished ELT bracket installation - 2 hrs

09-28-2012:  Nutplates on F715 seat ribs- 1 hr

09-29-2012:  Deburred and painted various interior parts, riveted F715 to bottom skin - 4 hrs

09-30-2012:  Center fuselage joined to aft fuselage - 2 hrs

10-01-2012:  Painted left side skin, riveted baggage ribs to F706 bulkhead - 2 hrs

10-02-2012:  Riveted center bottom skin to aft bottom skin, riveted F704H to side skin - 2.5 hrs

10-03-2012:  Firewall preparation, fuselage reassembled, except fwd bottom skin - 3 hrs


Fwd Fuselage Riveting (31.5 hrs)

10-04-2012:  Fwd fuselage riveting - 2 hrs

10-12-2012:  Fwd fuselage riveting - 3 hrs

10-13-2012:  Fwd fuselage riveting - 7 hrs

10-14-2012:  Fwd fuselage riveting - 4 hrs

10-16-2012:  Fwd fuselage riveting - 1 hrs

10-17-2012:  Fwd fuselage riveting - 3 hrs

10-18-2012:  Fwd fuselage riveting - 3 hrs

10-19-2012:  Fwd fuselage riveting - 1 hr

10-20-2012:  Fwd fuselage riveting - 2 hrs

10-21-2012:  Finished fwd fuselage riveting, ready to flip - 2 hrs

10-22-2012:  Flipped the canoe. Misc. wrapping up work - 1.5 hrs

10-23-2012:  Riveted the remain rivets in the aft fuselage - 2 hrs


Aft Deck and Top Skins

10-24-2012:  Drilled aft deck, fabricated spacers - 2 hrs

10-25-2012:  Primed aft deck and spacers, work on rails and F655 gusset - 3 hrs

10-26-2012:  Canopy deck fitted - 3 hrs

10-27-2012:  Riveted aft deck, other misc. task  - 3 hrs

10-28-2012:  Fitted F695 gusset, riveted arm rest to F705 bulkhead - 3 hrs

10-29-2012:  Riveted F695 gussets and F728 vertical angle - 2.5 hrs

10-31-2012:  Shoulder harness attachment F636, elevator bell crank F635 - 2 hrs

11-01-2012:  Riveted F708 to aft deck, riveted gussets for F706 and F707 - 2 hrs

11-02-2012:  Fit and drilled aft top skin - 2.5 hrs

11-03-2012:  Fit and drilled fwd top skin, and gusset F788 - 3 hrs

11-04-2012:  Fitted and drilled F6111 skin reinforcement, riveted F750 baggage cover - 3 hrs


Cabin

11-08-2012:  Trimed and fitted F652 and F751 baggage bulkhead - 2.5 hrs

11-10-2012:  Drilled baggage bulkhead to F706, started installing nutplates - 2.5 hrs

11-11-2012:  Underseat and baggage floor conduit - 3 hrs

11-13-2012:  RTV between conduits and brackets - 0.5 hr

11-14-2012:  Riveted baggage floor, installed bellcrank - 3 hrs

11-15-2012:  Installed rudder cable, worked on wear block - 1.5 hrs

11-17-2012:  Wear blocks, Vans static port, seat floors and hinges- 3 hrs

11-18-2012:  Aft seat floor assembly- 3 hrs

11-25-2012:  Seat backs (combined work from 11/22 to 11/25) - 8 hrs

11-28-2012:  Seat back braces - 1.5 hrs

12-01-2012:  Misc. work on cargo side wall, seat ribs - 2 hrs

12-02-2012:  Aft seat floors riveted - 3 hrs

12-03-2012:  Flap bearing block installation - 3 hrs

12-04-2012:  Flap control - 2 hrs

12-05-2012:  Flap actuator - 1 hr

12-06-2012: F785A and F785B drilled- 1 hr

12-07-2012:  Flap actuator support F766 assembly done - 2 hrs

12-08-2012:  Flap control system  - 4 hrs

12-16-2012:  Worked on wings, See entry in wing section


Wing Mating

02-02-2013: Organized garage, moved wings and fuselage for mating - 2.5 hrs

02-03-2013: Fuselage lower gusset F7114-R - 1.5 hrs

02-06-2013: F7114 bolted - 1 hr

02-08-2013: Prepare for wing mating - 1 hr

02-09-2013: Wings are mated to fuselage - 4 hrs

02-17-2013: Left rear spar drilled to 1/4" - 1 hr

02-18-2013: Rear spars drilled to final size - 2.5 hrs

02-21-2013: Control stick installed - 2 hrs

02-23-2013: Bottom fuselage skin drilling, fuel tank brackets, wing root fairing - 4 hrs

02-24-2013: Finished wing root fairing - 3 hrs

02-25-2013: Hang flaps and ailerons - 1 hr

02-26-2013: Aileron push rods installed and adjusted - 1.5 hrs

02-27-2013: Flap push rods fabircated - 1.5 hrs

02-28-2013: Right side push rod egress hole - 2 hrs

03-02-2013: Left side push rod egress hole and fuel vent line - 3 hrs

03-03-2013: Fuel vent lines - 3 hrs

03-04-2013: Fuel lines - 3 hrs

03-05-2013: Brake reservoir installed - 1 hr

03-07-2013: Elevator push rod and horizontal stab spacers - 2 hrs

03-08-2013: Trimmed horizontal stab skin to make for elevator movement - 2 hrs

03-09-2013: Mounted horizontal stab and elevator - 4.5 hrs

03-10-2013: Clamped Mounted vertical stab  - 1.5 hrs

03-11-2013: Vertical fin positioned  - 1 hr

03-13-2013: Drilled vertical stab  - 3 hrs

03-17-2013: Vertical stab and rudder mounted, worked on rudder stop   - 2.5 hrs

03-18-2013: Rudder stop, but need to rework  - 2 hrs

03-19-2013: Fuel line cover support   - 1 hr

03-21-2013: Re-made rudder stops  - 1 hr

03-23-2013: Wing unmated  - 4 hrs


After Wing Removal

03-24-2013: Riveted fuel line cover support brackets - 1 hr

03-25-2013: Fwd covers - 2.5 hrs

03-26-2013: Fwd covers - 1 hr

03-27-2013: Fwd covers - 2 hrs

03-28-2013: Fwd covers painted - 1.5 hrs

03-29-2013: Installed nutplates on fwd covers - 2 hrs

03-30-2013: Fuel pump and fwd deck - 5 hrs

03-31-2013: fwd deck superstructure clecoed together - 2 hrs

04-01-2013: Fwd top skin drilled - 1.5 hrs

04-02-2013: Fwd top skin deburred, except edge finishing - 2 hrs

04-03-2013: Superstructure deburred and primed, rudder pedal installed but not torqued- 3 hrs

04-04-2013: Comm radio antenna installation - 1 hr

04-12-2013: Panel Design - 4 hrs

04-13-2013: Static line and Dynon ADAHRS mount - 6 hrs

04-14-2013: ADAHRS mount #2 - 3 hrs

04-15-2013: Brake line installed - 3 hrs

04-16-2013: SV1 vent installed, started roll bar installation - 2 hrs

04-27-2013: Fuel system, fuel valve spacer, fuel pump tubing, trim cable - 4 hrs

04-28-2013: Elevator trim, top aft skin deburring and dimpling  - 3 hrs

05-05-2013: Terminal block on sub-panel, studying wiring diagram  - 3 hrs

05-08-2013: Cut instrument panel  - 2 hrs

05-09-2013: Cut instrument panel  - 1 hr

05-11-2013: Wiring  - 2 hrs

05-12-2013: Wiring  - 3 hrs

05-14-2013: Misc. riveting, bent firewall - 1.5 hrs

05-15-2013: Cut panel for Dynon Intercom and comm radio - 1 hr

05-16-2013: Finished switch holes - 1.5 hrs

05-17-2013: Instrument panel work - 1.5 hrs

05-18-2013: Stick grip wiring and installation - 3 hrs

05-19-2013: Manual aileron trim system, set some superstructure rivets - 3.5 hrs

05-22-2013: Fwd superstructure riveted - 2 hrs

05-23-2013: Wiring, no pictures - 2 hrs

05-24-2013: Continue wiring work - 3 hrs

05-25-2013: Continue wiring work - 3 hrs

05-27-2013: Wiring work, installed and powered on SkyView for the first time - 2 hrs

05-29-2013: Terminated autopilot wiring - 1.5 hrs

05-30-2013: Installed Dynon transponder and EMS - 1.5 hrs

05-31-2013: Prosealed terminal block for wing wiring - 2 hrs

06-01-2013: Transponder antenna installation and wiring, stick wiring - 2.5 hrs

06-02-2013: Terminated wires at wing root - 3 hrs

06-06-2013: Finishing wiring in the center and aft fuselage - 1.5 hrs

06-07-2013: Final preparation for riveting top aft skin - 2 hrs

06-08-2013: Top aft skin riveted - 2.5 hrs

06-09-2013: Fwd top skin of aft fuselage riveted - 3 hrs

06-10-2013: Trying to fix the clinched rivet using pop rivets, making it worse - 1.5 hrs

(06-12-2013:) finishing work

07-08-2013: Fabricated F-793 angle for vent support - 1 hr

07-22-2013: Panel removed for deburring, worked on the vent outlet - 2 hrs

07-25-2013: Primed and prepared panel and vent support brackets for final riveting - 2 hrs

09-04-2013: Deburred and dimpled top fwd skin - 2 hrs